High-capacity mixing bucket
In the background, the steel frame of the farm building.
Computer-generated image.
Batches of 750 to 2,000 l, made on site, far from a batching plant.
The bucket mixes, then pours through its chute at the pouring point.
The carrier is calculated on the concrete it lifts, not on the stated volume.
Other names for this tool: 1000-litre mixing bucket, 2000-litre mixing bucket, high-capacity concrete mixer bucket, loader mixing bucket, telehandler mixing bucket, hydraulic concrete mixer, concrete bucket.
- Family
- Recycling and recovering
- Tub
- From 750 to 2,000 l, in five sizes
- Unladen weight
- From 920 to 1,950 kg depending on the tub
- Functions
- Mixing by hydraulic blades; discharge through a chute
- Carrier machine
- Wheeled loader, telehandler or excavator, calculated in the study
What it is for
Livestock building slab, platform, foundation block:
some jobs need cubic metres of concrete, far from a plant.
The high-capacity mixing bucket makes this concrete on site, in batches of 750 to 2,000 l.
Hydraulically driven blades mix cement, aggregate and water in the tub.
The concrete comes out through a discharge chute, at the pouring point.
No truck mixer to wait for, no journey between the plant and the site.
Five tub sizes
The tubs hold 750, 1,000, 1,500, 1,800 or 2,000 l.
For example, the 1,000 l tub weighs around 1,000 kg empty.
The volume is chosen on what has to be poured per shift.
Three families of carrier
The bucket fits on a wheeled loader, a telehandler or an excavator.
The coupler is confirmed in the study:
loader coupler, telehandler coupler or excavator mounting plate.
The calculated carrier
Empty, the bucket weighs from 920 to 1,950 kg depending on the tub, and the concrete adds to that.
So the carrier is not chosen on the volume alone.
It is calculated in the study, on the concrete load and the machine's lifting capacity.
The discharge chute
The concrete comes out through a chute and flows into the formwork, with no skip or wheelbarrow between the mixer and the slab.
For small volumes, see the mixing bucket for compact loaders, or the mixing bucket for 2.5 to 8 t excavators.
The empty weight is only the start. A tub full of concrete weighs far more than the bucket alone, and it is this total that the machine lifts.
The lifting capacity is read with the tub full, at the pouring height and reach.
On which machine?
It fits on a wheeled loader, a telehandler or an excavator.
The machine class is calculated in the study, according to the concrete load:
we do not give a tonnage without this calculation.
The coupler or mounting plate is confirmed with the machine's data sheet.
What the tool does
A steel tub from 750 to 2,000 l, with hydraulically driven blades.
The concrete comes out through a discharge chute.
Empty, the bucket weighs from 920 to 1,950 kg depending on the tub:
around 920 to 950 kg for 750 l, around 1,900 to 1,950 kg for 2,000 l.
What is needed on the hydraulic side
It needs an auxiliary hydraulic line on the machine, in continuous operation during mixing.
The flow and pressure are not published for these tubs:
they are checked in the study, with the machine's data sheet.
Figures taken from 2 ranges on the market.
Your study sets the exact value for your machine.
Have your machine checked.
Give us the machine, its coupler, its hydraulic circuit and its lifting capacity.
Tell us what you are pouring, and how much per shift:
we calculate the tub and the carrier together.
-
Your machine
Loader, telehandler or excavator:
its make and its model. - The auxiliary circuit Its flow in l/min and its pressure in bar.
- The coupler in place Its system, or a photo.
- The lifting capacity The machine's load chart or data sheet.
- The work Concrete, lean concrete or mortar, and the volume to be poured per shift.
Without these details, the study still begins:
we will ask you for them.
Or call 01 84 16 55 49 · our lines are open 7 days a week, from 7h to 22h.
Written study within 3 working days, once the file is complete.
What determines the choice
-
01 — The volume per shift
The tub is chosen on what has to be poured per shift:
not on the total volume of the job. -
02 — The concrete load
With the tub full, it is the load that chooses the carrier:
the empty weight is only part of it. -
03 — The carrier
Loader, telehandler or excavator:
each has its own coupler, pouring height and lifting capacity. -
04 — Continuous flow
The blades turn throughout the batch:
the flow is counted as continuous, not peak. -
05 — Supplies
Water, cement and aggregate in quantity, close to the pouring point:
it is this logistics that sets the pace.
What is checked before ordering
- The lifting capacity With the tub full, at the pouring height and reach.
- The hydraulic circuit An auxiliary line, its flow and its pressure measured on the machine.
- The interface Loader coupler, telehandler coupler or excavator mounting plate.
- Cleaning A water reserve to rinse the tub at the end of the shift.
- Family
- Recycling and recovering
- Carrier machine
- Wheeled loader
- The trade
- Agriculture